March comes and I thought we'd never get here - I almost have a house that looks like a house now.
The central heating system gets installed (although not tested yet - not all the radiators are on the wall)
The new plasterboard walls in many of the rooms get plastered. This includes, all of the three bedrooms, the upper hallway, the kitchen and the lower lounge.
The bedrooms and upper hallway are all painted. New doors go on for all of the rooms upstairs.
The electrican completes the circuits for upstairs - we now have lights and power to all the upper rooms.
The under floor heating goes in in the kitchen.
The new kitchen floor tiles are laid and grouted.
The kitchen and bathrooms arrive on site (OMG where am I going to put everything!).
The paint starts going on the outside.
The kitchen starts to go in.
The electrican completes the initial phase of circuit provision to downstairs. We now have light and power to the power floor as well!.